Land use & zoning

Fauquier planners recommend denial of Gigaland campus near Remington

Confirmed

Date
2025-06-18
Location
Fauquier County, VA
Category
Land use & zoning

FauquierNow reported June 20 that the commission voted 4–1 at its June 18 meeting after a three-hour public hearing. The proposed seven-building campus occupied 202 acres south of Lucky Hill Road outside Remington town limits. The application included water-treatment infrastructure, two wells, a storage tank and four electrical substations; these were proposed components, not completed utilities. This was a recommendation, not final project rejection, and the verified site is in the county rather than within Remington. The reporting does not establish that the proposed facilities would run exclusively AI workloads.